Can Jordan get through the next four summers without Israeli water?

Opinion · Ending the extra Israeli supply was the right call. The desalinated water from Aqaba arrives in 2030, and the years in between depend on decisions at home.

King Talal Dam, Jordan's largest reservoir, on the Zarqa River.
King Talal Dam, Jordan's largest reservoir, on the Zarqa River. Anark75, CC BY-SA 3.0, via Wikimedia Commons

Key points

  • The 2021 add-on deal for an extra 50 million cubic metres a year of Israeli water has expired without renewal.
  • Jordan has about 61 cubic metres of water per person a year, against a 500-cubic-metre scarcity line, and most homes get water once a week.
  • The Aqaba carrier will deliver about 300 million cubic metres a year from the end of 2030, at a total investment of 6.7 billion dollars.
  • Donors asked for a tougher crackdown on illegal wells before completing the financing.
  • The government should publish its alternative plan with yearly volumes and report well closures every quarter.

Ten days ago Prince Faisal bin Hussein laid the cornerstone of the Aqaba desalination and conveyance project on the King's behalf. Officials called it one of the largest infrastructure projects since the East Ghor Canal of the 1950s, and it was a good day for Jordan. It also pulled attention from a harder question, one that most households here will feel long before any desalinated water reaches them. How do we get through the next four summers?

Start with what has been lost. The add-on agreement of 2021, under which Israel sold Jordan an extra 50 million cubic metres a year on top of the 50 million guaranteed by the 1994 treaty, has expired and has not been renewed. Fanack Water reported in April that Jordan had asked in 2024 for a one-year extension and that Israel attached political conditions to it, among them a softer tone and the return of full diplomatic engagement. No extension followed. After Gaza, I think refusing those terms was the only position any Jordanian government could have taken. It still has a cost, and we should say so.

What the country is working with

Jordan uses roughly a billion cubic metres of water a year, most of it on farms. Rainfall averages about 100 millimetres. The Green Climate Fund puts Jordan's water availability at 61 cubic metres per person per year, against the 500-cubic-metre line that hydrologists use to define absolute scarcity. Most households receive piped water once a week. In a system that thin, 50 million cubic metres is a serious loss, about half of what the Disi aquifer pipeline, the last great project, delivers each year.

The new carrier is meant to change the scale of all this. It will desalinate about 300 million cubic metres a year at Aqaba and pump the water roughly 418 kilometres north, lifting it up to 1,100 metres above sea level on the way. Meridiam, which leads the mostly French consortium holding the 30-year concession, puts the total investment at 6.7 billion dollars. The Green Climate Fund has committed 295 million dollars in concessional money, its largest single-country commitment, and more than twenty lenders sit alongside it, the EBRD, the European Investment Bank and the US Development Finance Corporation among them. A 280-megawatt solar plant is meant to power about 80 per cent of the desalination plant itself. The Jordanian Social Security Investment Fund is a shareholder in the project company.

The first water is due by the end of 2030. Everything I have to say follows from that date.

The years in between

Until then Jordan must manage the loss of Israeli water with what it already owns. The Jordan Times reported that the government drew up an alternative plan in 2025, at the prime minister's direction, to replace the Israeli purchases. The details made public so far are modest: more cooperation with Syria through the joint water platform launched in September 2025, a cloud-seeding study for the Yarmouk basin, and attention to Jordan's share at the Wihdeh Dam. These are sensible steps. None of them replaces 50 million cubic metres on its own.

The tool that matters more is one we rarely discuss in public, which is water pumped and never billed. The National reported that American and European donors asked for a tougher crackdown on illegal wells, many of them in tribal areas, before they completed the financing. I read that as a judgment. The people paying for Jordan's largest project looked at our system and decided that theft and losses are a problem of the same order as supply, and I think they are right. Every illegal well closed between now and 2030 buys time that no ceremony can.

Here the politics get difficult. Closing wells means confronting landowners and, in some areas, families with standing and influence, and telling farmers that pumping fossil groundwater for low-value crops is something the state can no longer tolerate. No government enjoys that. The alternative is to ask urban households, already living with weekly supply, to absorb the loss alone through longer gaps between deliveries.

Independence has a price

Prime Minister Jafar Hassan described the carrier as a step towards water independence. I agree with the direction, and I believe most Jordanians do. For three decades our water security has depended partly on a neighbour whose decisions we cannot influence and whose conditions grew more political with each crisis. Ending that dependence is a sovereign choice, and Jordanians have accepted it.

Independence will come slowly and it will cost money. The carrier ties the country to a long pipeline across the desert, a large pumping and energy bill, international lenders and a concessionaire's performance for three decades. Officials have said themselves that the project will lessen Jordan's water problems and will not end them. That is a fair description, and the public deserves to hear it repeated rather than buried under the language of a historic milestone.

What I would ask of the government is modest. Publish the alternative plan in full, with the volumes each measure is expected to deliver every year until 2030. Report how many illegal wells are closed each quarter and how much water that recovers. And tell people plainly what summer supply will look like next year, because Jordanians are used to scarcity. What wears down their trust is the sense that the hard numbers are kept from them while the good news arrives with a ribbon and a speech.

Stopping the purchase of water on political terms was the right decision. Making it work over the next four years will depend on choices taken at home, and I would like to see them get as much attention as the cornerstone in Aqaba received.